It’s been a turbulent year for the residents of Port Talbot, in an area known for its massive steelworks site, which long served as a cornerstone of the South Wales community. For more than 100 years, the steelworks site has dominated the skyline, with its huge blast furnaces instantly recognisable to those driving past on the M4. Almost everyone in the town knows someone who worked at the site at one time or another.
There has been much anxiety for residents since the closure of those furnaces in September 2024, after owner Tata announced a switch to greener technology, as around 2,000 redundancies are expected for workers as a result. The impact of the closure on Port Talbot cannot be understated, with some fearing it could change the very fabric of the area. It affects businesses in the wider supply chain, but also the very sights and sounds that have become synonymous with this part of Wales.
However, despite the uncertainty currently faced by many, some hope there could yet be light at the end of the tunnel for this historic industrial area, with a number of plans in the works that could bring in jobs and investment. Here are some major projects currently in the pipeline for Port Talbot.
Tata’s electric arc furnace
Despite the closure of its two massive blast furnaces, a planning application has already been submitted by Tata Steel for a new £1.25bn electric arc furnace to be built at the Port Talbot steelworks site. The proposal was submitted to the Neath Port Talbot Council planning department in November 2024. If approved, it could see the creation of a 3.2mn-tonne capacity electric arc furnace. A contract has already been signed by Italian firm Tenova to build it.
Operations with the electric arc will mean no ‘virgin steel’ created from scratch can be made at the site moving forward, and not as many members of staff will be required to run it. But the plans say the new furnace will still have the capacity for 3mn tonnes of steel each year through melting scrap steel.
The plans also say that, if approved by the local planning authority, the new electric furnace could reduce the site’s steel-making carbon emissions by 90%. This is equivalent to 5mn tonnes of CO2 a year. The aim is for it to be operational sometime in 2027.
The Celtic freeport
Plans to create a new freeport in the Celtic Sea area have been launched by Neath Port Talbot Council, as part of a joint bid between the Associated British Ports, Neath Port Talbot and Pembrokeshire councils, and the Port of Milford Haven. Freeports are described as special areas within UK borders where different economic regulations apply, such as tax incentives for eligible businesses.
At a recent meeting council members heard how the site could provide a huge boost to the economy of Neath Port Talbot and the whole of Wales, with its new freeport and a potential offshore floating wind-farm based in the Celtic Sea.
Supporters of the development, which was first approved by the UK Government in March 2023, have said they believe the site could generate more than £5.5bn worth of investment and around 16,000 jobs, once fully up-and-running in the coming years.
[Editor’s note: data regarding freeports suggests that they move jobs from one area to another but do not create significant new employment as claimed. There is a renewed commitment to freeport developments in the UK after a past programme was closed down due to being ineffective, but they do bring complex concerns with them. You can read more about them in the Bylines Network Freeports Gazette.]
Project Dragon jet fuel plant
Plans to build a major jet fuel facility on a former industrial brownfield site at Port Talbot’s Crown Wharf were approved in March 2024. It is hoped that the facility could create more than 150 full-time jobs, with more business generated further down the supply chain.
The proposal named Project Dragon is led by US-based firm LanzaTech, and will see the creation of a sustainable aviation fuel production facility based in Port Talbot. It’s described as an “exciting application” that could create well paid jobs. Developers have said the site could produce as much as 100mn litres of sustainable aviation fuel per year, using an alcohol-to-jet facility to turn sustainably sourced ethanol into aviation fuel.
Production at the facility is hoped to begin in 2026, though a statement from the company notes that this timeline is “subject to securing the legislation, investment and off-take agreements that are needed to move forward to a final investment decision”.
South Wales Industrial Transition from Carbon Hub (SWITCH)
Elsewhere at Harbourside Port Talbot, plans have been submitted for building a £20mn industrial research facility. The South Wales Industrial Transition from Carbon Hub (SWITCH) is part of the Swansea Bay City deal, and would see the construction of a purpose-built research centre for decarbonising the metal and steel industry.
The project will be led by Neath Port Talbot Council in partnership with Swansea University, with the proposed centre described as an “open access centre establishing a collaborative network of expertise across academia, industry and government, aiming to accelerate the region’s transition to net zero”.
The plans for the research building envisage facilities including workshops, welding zones, mechanical testing zones, and laboratory space, as well as offices, reception, and breakout spaces. They will go before the council’s planning department for a decision in the coming months.