There has been a bridge over the River Usk in Newport since around 1100. From that time, successive timber bridges have provided crossings on high timber piers. These piers were required owing to the enormous tidal range of the river level at 42ft (13m). Newport has the highest tidal range on any river of any city in the world.
The town was slow to convert the timber structures into a stone bridge. Eventually, a public meeting was held in Usk in 1789, where it was agreed to seek parliament’s authority to use the county rate to erect a stone bridge in Newport.
In 1791, the Monmouthshire justices invited designs for a stone structure; four were submitted, and the winning submission was from the architect John Nash. Best known for his work in London and Brighton, Nash is not popularly appreciated for his work in Wales or as a bridge builder; however, he built bridges in Cardiganshire, in Trecefel and Aberystwyth.
Nash’s bold design
Nash submitted plans and a model to the justices, proposing to construct an arch bridge crossing the river in a single span. The model and plans are lost, but we are fortunate that Gwent Archives holds the drawing for the timber centring required to construct the arch, which also provides much information about the bridge itself (see the image above). The design was nothing less than revolutionary, crossing such a wide river without the need for supporting piers.
The bridge designed was an arc of a circle approximately 310ft (94m) in diameter, with a span of roughly 285ft (86m). The crown of the centring would have stood about 100ft (30m) above the low water level, and as the tidal range is approximately 42ft (13m), would have left roughly 58ft (18m) between the high water level and the crown. Above the crown, the bridge structure would have added at least another 7ft (2m). This gigantic structure would have towered above the river next to the castle, but where did Nash get his idea from?
The famous bridge in Pontypridd
There were few precedents for Nash to follow with his design. One that must surely have been a significant influence was the famous bridge that survives in Pontypridd, about 15 miles (24km) away, built by William Edwards in 1756 and spanning 141ft (43m) in a single arch. Unlike Edwards’ previous three unsuccessful attempts at the same site, the bridge is light and elegant and has stood the test of time.

Drawing by John Preston Neale, held by The National Library of Wales.
(In the public domain)
The bridge’s width of 11ft (3m) was adequate for its day, but the steepness of the roadways meant that wagons and carriages needed to use a cumbersome ‘chain and drag’ system to slow down the descent from the crown, which was described in 1838:
“When a carriage reaches the centre of the bridge, one end of the chain is attached to the hinder part of it, the other being secured to the drag, upon which a boy generally places himself, so that as the carriage descends upon one side the drag is pulled up the other, and this relieves the horse in descending.”
Work on the bridge begins …
Surviving accounts reveal expenditure on the bridge beginning in 1790, and included planning, materials, and advertising. With no supporting piers, the bridge required substantial abutments in the riverbanks, and, due to the tidal range, Nash could not find contractors willing to take on such a risky venture. He began constructing a cofferdam, but in May 1792 the scheme was abandoned following a ‘county meeting of gentlemen and freeholders’. They agreed to pay £700 for the work to be completed and sought a new design. It appears that the ambitious design presented too many risks for the justices, who had eagerly embraced the bold design the previous year.
Later developments
Soon after the town cancelled Nash’s contract, it commissioned a different stone bridge constructed in 1801 by David Edwards, the son of William Edwards who constructed the famous bridge in Pontypridd mentioned above. That bridge had five arches and was replaced by the present one in 1927. He also built the surviving bridge at Caerleon, which was completed in 1812 with three arches.
Nash’s ideas were picked up soon afterwards by a committee formed in Sunderland to promote the construction of a bridge over the mouth of the River Wear. His plans were considered alongside others by the committee, which discussed whether to build one arch or two, with the option of a single arch bridge exceeding 200ft (61m). That would have set a new world record for a surviving bridge, while remaining smaller than Nash’s Newport design.
In the event, they chose an iron single span bridge. This pushed the boundaries of the new technology afforded by the developments in iron production, spearheaded by the world’s first iron bridge at Ironbridge, Shropshire, in 1779. The Sunderland bridge opened in 1796 and was acclaimed as the world’s largest single-span bridge at 236ft (72m).
Despite the availability of modern materials, it was not until 1874 that the world had a bridge with a greater span than Nash’s planned bridge for Newport. That was the enormous Eads Bridge connecting Missouri with Illinois (in the USA), but by then, the torch had been passed to a new generation of steel bridge builders.
What if the Newport bridge had been built?

Image based on a print by Edward Pugh. Newport Museum and Art Gallery
The records for the Pontypridd bridge illustrate the difficulties users faced in transporting heavy loads across such a high arch bridge. Logic dictates that similar problems would have occurred at Newport, but on a much larger scale.
Another potential issue would have been the volume of use as the town expanded. The Monmouthshire Canal reached Newport in 1796 and passed the castle. the Sirhowy Tramroad then arrived in 1805. These developments enabled a substantial increase in the volume of coal and iron reaching the ships at the Newport quayside, and the town grew accordingly throughout the 19th century. It follows that traffic on the town bridge increased, potentially exacerbating the problems already likely to occur with Nash’s bridge.
Until 1892, there was a slight depression on the approach to the first stone bridge from the west, known as ‘the dip’, where wagons would get stuck and require assistance to pull them out, especially during wet conditions. Again, this suggests that Nash’s bridge would have struggled to meet growing transport demand and would have required replacement by a more practical option.
We will never know whether the justices foresaw these operational problems as well as the construction issues when they cancelled the contract. While their decision was probably the right one for the town’s transport, it deprived Newport of the honour of having the largest bridge ever built. Before Nash’s time, the widest bridge span was at Trezzo sull’Adda in Italy, built in 1377, but destroyed by military action in 1416. With an estimated span of 239–252ft (72–76m), it was at least 33ft (10m) shorter than Nash’s design. No stone bridge anywhere exceeded the span of Nash’s design until the 1905 Plauen bridge in Germany at 295ft (90m). The opportunity that slipped through the fingers of the Newport justices in 1792 deprived the town of its fame for an iconic bridge until 1906, when the transporter bridge opened.
Author’s note: Further details of Nash’s bridge can be accessed via the websites below:
Newport Past and Friends National Museum Wales

Bylines Network Gazette is out!
The latest Bylines Network Gazette is out now. Become a Friend of Bylines Network or upgrade to a paid Substack subscription, and you will get access to a vital collection of citizen articles and stories.
Journalism by the people, for the people.